18 Oct 2016 1 min read
Kefi Minerals expects production at Tulu Kapi in mid-2018
Kefi Minerals has received a Front End Engineering and Design proposal for US$68 million from Lycopodium for the EPC contract to build a mine at its 95%-owned Tulu Kapi gold project, in Ethiopia. Including contingencies and provisions for non-Tulu Kapi costs, the total capital estimate for the project has been increased to approximately US$150-160m. The […]
-
02 Jun 2016 1 min read
Kefi reduces estimated capital to build its Ethiopian gold mine: KEFI
Kefi Minerals has reduced the estimated funding required to build a mine at its 100%-owned Tulu Kapi gold project, in Ethiopia, from US$145.0 million in the 2015 definitive feasibility study to US$131.7 million, principally through a change in the life-of-mine plan. With an open pit processing ore by conventional CIL at a revised rate of […]
-
28 Sep 2015 1 min read
Ethiopian Government to participate in funding of KEFI’s mine
KEFI Minerals has reported that it is likely to fund the whole of the US$120 million required to build a mine at its 100%-owned Tulu Kapi gold project, in Ethopia, at the project level through a combination of debt, gold streaming and equity funding as well as the participation of the Government of Ethiopia, which […]
-
17 Aug 2015 1 min read
KEFI reviewing construction and financing options for Tulu Kapi gold project
Following the publication of a definitive feasibility study in June this year on its 100%-owned Tulu Kapi gold project, in Ethopia, KEFI Minerals is now reviewing bids from prospective Engineering, Procurement and Construction Management (EPCM) contractors as well as looking at options to lower the estimated peak capital investment of US$130 million to around about […]