Kefi Minerals has received a Front End Engineering and Design proposal for US$68 million from Lycopodium for the EPC contract to build a mine at its 95%-owned Tulu Kapi gold project, in Ethiopia. Including contingencies and provisions for non-Tulu Kapi costs, the total capital estimate for the project has been increased to approximately US$150-160m.

The open pit, processing ore by conventional CIL at a rate of 1.5 Mt/y, is expected to commence production in mid-2018 at a life-of-mine rate of 100 koz/y of gold.

The company has raised £3.8m, primarily for resettlement of the Tulu Kapi community. The board is currently considering financing proposals for the project.

Kefi Minerals expects production at Tulu Kapi in mid-2018: KEFI

Leave a Reply

Your email address will not be published. Required fields are marked *

Please review our cookie, privacy & data protection and terms and conditions policies and, if you accept, please select your place of residence and whether you are a private or professional investor.

You live in…

You are a…